active cc number online store | bellcoconstructiongroup.com

print mail CDM Projects - global warming ice

Montenegro / Andrijevica, Berane, Rozaje ENERGY GENERATION FROM WOODY BIOMASS IN NORTHERN MONTENEGRO Power generation

The objective of the project is the construction of a regional electrical generator with 3 MW installed net capacity and annual electrical generation of around 23,4 GWh exported to the grid, using biomass residues (wood from forest and wood from sawmills) as fuel. The available biomass residues could be obtained from the wood processing industry and mainly from forests, owned by wood processing companies.

CURRENT STATUS: Feasibility study done in 2007. » More details

Montenegro / Berane AFFORESTATION OF DEGRADED LAND Forestry

The objective of the project is the afforestation of 360 ha of degraded agricultural and pasture land. The project area is located in the north region of the Republic, on the territory of the Municipality of Berane, along the riverside, in the area of the upper river course of the river Lim. Currently, the project area is classified as grassland, with vegetation cover that includes presence of shrubs.

Montenegro / Nikšić, Pljevlja INTEGRATED PROJECT AT PLJEVLJA AND NIKŠIĆ LANDFILL SITES - GHG REDUCTION THROUGH BIOGAS RECOVERY AND COMBUSTION Methane recovery

The aim of this project activity is to reduce methane emission from two dump sites by converting it into carbon dioxide that impacts global warming 21 times less, simultaneously reducing odour and explosion risk at the landfill. The proposed dump sites are located in two municipalities, Pljevlja, situated in the northern region of the Republic of Montenegro and Niksic located in the central region of the Republic.

CURRENT STATUS: PDD finished. » More details

Montenegro / Berane INTEGRATED HYDROELECTRIC PROJECT Power generation

The Electric Public Power Company of Montenegro (EPCG) is in the process of establishing the list of potential SHPP projects that should be offered on concession by the end of this year. The project developer who obtains the concession on the construction of SHPPs could develop a CDM project with a significant potential of CERs, by means of bundling a couple or a few SHPPs on one river flow. This potential depends on the total installed capacity of the bundled projects, on the modality of bundling, as well as on the value of the carbon emission factor for Montenegro.

CURRENT STATUS: Project Idea scouted in 2007. No additional information available. » More details

Montenegro / Berane, Bijelo Polje, Danilovgrad, Herceg Novi, Niksić, Plav, Pljevlja, Tivat, Ulcinj ENERGY EFFICIENCY IN STREET LIGHTING Energy efficiency

The project activity consists of improving the existing street lighting system in nine municipalities in Montenegro, with approximately 300.000 inhabitants, by means of more efficient lighting technologies. According to the EE Strategy, by providing a good selection of the lightings and automatic lighting regulation, it is possible to obtain energy savings of 20 - 25% in this field.

CURRENT STATUS: Draft PDD has been done, project doesn't meet the CDM's additionality criteria. » More details